In Design: Route 7 and Route 9 Eastbound Ramp Extension in Loudoun County
Cost and schedule ►
Public outreach ►
 
  
  
      
 
    
    
   
    The project will extend the acceleration lane from Route 9 onto eastbound Route 7 in Loudoun County to make it easier for drivers to merge into traffic from the ramp.
This improvement is part of the Strategically Targeted Affordable Roadway Solutions (STARS) Route 7 Corridor Improvement Study completed in December 2017.
Estimated Costs
Preliminary Engineering: $610,000
Right of Way: $44,000
Construction: $2.3 million
Total: $2.7 million
The project is financed with federal and state funding.
Benefits
This project aims to improve safety and relieve congestion.
Major Milestones
Environmental Documentation (Programmatic Categorical Exclusion) Available - September 2022
Issue Notice of Willingness to Hold a Public Hearing- October 2022
Begin Right of Way Acquisition - Winter 2023/24 
Begin Construction - Winter 2024/25 
Resources
              
                    W. Calvin Britt, P.E.
Location & Design
                    703-259-2961
                    
              
                    Kimberly McCool, P.E.
Preliminary Engineering
                    703-259-3220
                    
Other relevant links:
Notice of Willingness to Hold a Public Hearing - October 2022
Programmatic Categorical Exclusion - 
Sept. 2022
Major funding source: Federal
Phase: In Design
UPC: 114103
State ID: 6007-053-198, P101
Federal ID: NCBP-5A01 (973)