Recently Completed: Columbia Pike and John Marr Drive Intersection Improvements in Fairfax County
Cost and schedule ►
Public outreach ►
Please note: This project was completed in February 2023.
This project upgraded the signalized intersection of Columbia Pike (Route 244) and John Marr Drive.
The improvements included:
- Traffic signal and curb ramp upgrades
- A new crosswalk across Columbia Pike
- Accessible pedestrian signals
At the intersection, Columbia Pike averages 25,000 vehicles a day and John Marr Drive averages about 8,400.
Estimated Costs
Preliminary Engineering - $70,000
Right of Way Acquisition and Utility Relocation - $190,000
Construction - $440,000
Total - $700,000
This project was financed with federal and state Highway Safety Improvement Program funding.
Benefits
This project aims to improve safety for pedestrians and drivers.
Major Milestones
Notice of Willingness to Hold a Public Hearing - May 2019
Begin Right of Way Acquisition - July 2020
Begin Construction - March 2021
Final Completion - February 2023
Resources
              
                    Paul Shaw
Traffic Operations
                    571-221-1320
                    
              
                    Nick Dais, P.E., PTOE
Traffic Operations
                    703-259-2237
                    
Other relevant links:
Major funding source: Highway Safety Improvement Program
Phase: Recently Completed
UPC: 112481
State ID: 0244-029-317, C501, P101, R201
Federal ID: HSIP-5A01 (952), HSIP-5B01 (144), STP-TS09 (301)
                Lat/Long: 38.832980, -77.189699
                
              
              
                
                
                Locality:
                
                Fairfax
                
                
                
                
            